Product Description
Basic Use: FlameChek Duct Insulation is a 11/2"
thick non-ceramic, glass fiber, hightemperature insulation blanket.
It is designed to be an easily installed double layer system for
grease duct applications requiring a onehour or two-hour rating.
FlameChek can be used in many commercial and industrial passive
fire protection applications such as kitchen exhaust grease ducts
in restaurants, stadiums, hospitals, prisons and other facilities
with commercial cooking operations.
Benefits:
This product is non-ceramic, flexible, simple to wrap around ducts
and encapsulated with a flame-resistant scrim specifically designed
to survive the rigors of installation.
FlameChek saves critical building space in commercial and industrial
applications, allowing for zero clearance from the duct insulation
to the interior surfaces of combustible construction. The product
also provides superior thermal and mechanical properties and simplifies
field installation.
FlameChekô Duct Insulation
Composition and Materials:
High-temperature glass-fibers created from a calcium, magnesium
and silica chemistry, combined with a proprietary fiber spinning
technology, produce a specialty hightemperature, completely inorganic
glass fiber
blanket. FlameChek Duct Insulation is fully encapsulated in a
glass scrim reinforced aluminum foil facing.
Sizes: FlameChek Duct Insulation is 1.5" thick and
available as 2' or 4' wide, 25' long rolls.
Technical Data:
Applicable Standards: Underwriters
Laboratories (UL) classified, zero clearance, two-hour fire-rated
grease duct enclosure system. Meets National Fire Protection Association
(NFPA) 96 requirements which allow for zero clearance from the
duct insulation to the interior surfaces of enclosures of combustible
construction.
Fire Resistance: Two layers (3" thickness)
of FlameChek Duct Insulation are required to achieve a two-hour
rating.
- Internal
Grease Duct Fire test (zero clearance, 2000æ F) according
to UL 1978 with 3" FlameChek Duct Insulation.
-
Grease Duct Through Penetration according to UL 1479 and Firestop
Test (see UL System No. C-AJ-7032) according to ASTM E 814;
F Rating = 3 Hours, T Rating = 3.
-
External Duct Fire Test, Fire Rating Enclosure Tested in accordance
with UL 263, ASTM E 119 and 2-hour fire ratings with 3"
FlameChek Duct Insulation.
-
Fire Hazard Classification: ñ (UL 723, ASTM E 84) Max.
Flame Spread Index; 25 Max. Smoke Developed Index; 50.
Required Materials
Floor
or Wall Assembly - Min. 4.5" thick concrete floor or min.
5.5"concrete or block wall.
Through Penetrant - 16 gauge or heavier steel duct.
Fire Protection System - consisting of:
-
Wrap Materials - Two layers of 1.5" thick FlameChek Duct
Insulation. Seal all cut edges of FlameChek Duct Insulation
with 4" wide pressure-sensitive aluminum foil tape.
Wrap the steel duct with two (2) layers of FlameChek Duct
Insulation. Cut each layer to size and tightly wrap directly
around duct with a minimum perimeter overlap of 3".
Stagger perimeter joints of outer layer of FlameChek Duct
Insulation from the perimeter joints of inner layer of FlameChek
Duct Insulation. Overlap longitudinal joints min. 3";.
Offset the longitudinal joint of outer layer approx. 10.5"
from longitudinal joints of inner layer. Temporarily secure
each piece of FlameChek Duct Insulation with 1"; wide
filament tape spaced max. 12" OC (10.5" OC recommended).
Annular space of 0.75" to 1.25" between insulated
duct and periphery of opening.
- Steel
Banding Straps - 0.5" wide by 0.015" thick Type
SS 302 banding straps and 0.5" wide by 1" long Type
SS 302 crimp clips. Straps max. spacing is 12" OC (10.5"
recommended). At least three steel banding straps per 24"
wide blanket.
-
Stainless Steel Mesh - Min. 0.011" thick Type SS 304
mesh tightly wrapped around face layer of FlameChek Duct Insulation
with min. 1" perimeter overlap. Extend mesh min. 4"
beyond floor or wall. Temporarily secure with 24 gauge steel
wire ties positioned 2" from top and bottom of mesh.
Secure mesh
with SS worm drive banding and hose clamps (item 3D) on 4"
centers, and locate at top and bottom plane of slab.
- Steel
Banding and Clamps - 0.5" wide by 0.030" thick Type
SS 430 worm drive banding and hose clamps.
-
Forming Materials ó Min. 3.5" thick FlameChek
Fiber Blanket firmly packed in opening to fill annular space
between FlameChek Duct Insulation surface and periphery of
opening. Annular space should be 1.25" to 1.75".
After packing, FlameChek blanket to be recessed from top of
floor or from both surfaces of wall as
required to accommodate Firestop Putty.
- Fill,
Void or Cavity Material - Min. 1" thick applied within
the annular space, flush with top surface of floor and with
both surfaces of wall. Install additional Firestop Putty so
a min. 0.5" crown is formed around wrapped duct and lapping
0.5" beyond periphery of opening.
Installation
FlameChek Duct Insulation has been designed to simplify field
installation. The system consists of two 1.5" layers of FlameChek
Duct Insulation (3" total thickness) applied directly to
the duct surface.
A 3" longitudinal and perimeter overlap is employed to eliminate
potential seams for fire penetration.
Until
the FlameChek Duct Insulation is permanently secured with stainless
steel bands, filament tape is used to temporarily hold the interior
and exterior layers in place during installation. Insulation pins
are recommended for duct spans greater than 24". Pins should
be attached to the bottom of the horizontal duct surface and on
vertical duct runs to prevent sagging of the material.